Medfield Heights Elementary School

project Summary

Visit the 21st Century Schools website to learn more about Medfield Heights Elementary School

This 79,899 sq. ft. replacement school project is necessitated by enrollment growth in North Baltimore and is in the Design Phase.  Design is expected to be complete in late March 2019 with construction beginning in late June 2019.  It is anticipated that the existing student population will swing offsite to the Chinquapin building in June 2019.  Substantial completion is scheduled for November 2020 and opening for students in January 2021.

Medfield PK-5

Project Director

Gary McGuigan

Project Executives

Eric Johnson