project Summary
The pedestrian spine underwent an approximately $5.1-million renovation. The pedestrian spine is a walkway that connects Oriole Park at Camden Yards to M&T Bank Stadium through the stadium parking lots B and C. The 975 ft. pedestrian spine was renovated to include enhanced security features, new hardscaping, a new impervious surface, new landscaping, and storm water improvements. The Gilbane Building Company was awarded the contract, and renovations were completed by August 2019.
Project Executives
Philip Hutson, CCM, LEED AP, Associate Vice President of Capital Projects and Planning
Project Manager
Kelly Smulovitz, P.E., CCM, LEED AP, Project Manager of Capital Projects and Planning
Construction Manager
The Gilbane Building Company
Project Budget
$5.1Million
Completion Date
August 2019