Circuit Court of Baltimore City Study of Alternate Use Programs

study summary

In June 2018, the Maryland Stadium Authority (MSA) approved a request from the Baltimore City Administrative Judge for MSA to conduct an Alternate Use Programs for the Circuit Court Complex (Complex) study. The study will include research and analysis of potential alternate use of the Complex.

Baltimore City Circuit Court Feasibility Study (2011)
Baltimore City Circuit Courthouse Study (2016)

Study Director

Gary McGuigan, Senior Vice President, Capital Projects Development Group

Study Manager

Al Tyler, Assistant Vice President, Capital Projects Development Group

Study Budget

$40,460.00

Completion Date

December 2018