Baltimore City Public Schools Construction

John Eager Howard Elementary: 2011 Linden Avenue, Baltimore, MD 21217

Project Summary:  The John Eager Howard community is very connected to its school, both as a place to foster students’ academic success and as a neighborhood resource and gathering place.

This school will be renovated and expanded, retaining its accessible common areas including its separate auditorium, gymnasium, and cafeteria and reconfiguring space in the adjoining recreation center. At the same time, academic wings will be renovated and expanded with new construction, resulting in grade-level classroom clusters with flexible areas for collaboration, project work, small and large group activities, and other best practices in teaching and learning for the 21st century.

With the recommended closure of Westside Elementary School after completion of construction at John Eager Howard and anticipated population growth in the neighborhood, enrollment at the latter school will increase. The newly renovated and expanded building will provide a welcoming and inspiring setting for both student learning and community engagement.

Visit the new 21st Century School Buildings Plan website for project updates.

Project Executives:
Gary A. McGuigan, Eric Johnson

Project Manager:
Tom Henderson (City School Partners)

Architect/Design:
Cho Benn Holback & Associates

Construction Manager:
J. Vinton Schafer & Sons

*Project Budget:
$34,000,000

Completion Date:
January 2018

Note: The budget is inclusive of contingencies, phasing, design, construction, FF+E, utilities, demolition/hazmat abatement, commissioning/LEED, testing & inspection and third-party inspection.